San Juan Road Interchange |
Description: Near Prunedale, from 0.4 mile south of Dunbarton Road (North) to 1.0 mile north of Cole Road. Convert to freeway and construct new interchange.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Monterey |
City | Aromas |
Zip Code | |
Senate District |
15 |
Assembly District | 28 |
Congressional District | 17 |
Caltrans District |
05 |
County/State Route | Monterey 101 |
Postmile Begin/End | 100 101.3 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 884 | 662 |
Peak Period Time Savings (minutes) | 6424 | 5479 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | David Silberberger | (805)549-3798 | david_silberberger@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | David Silberberger | (805)549-3798 | david_silberberger@dot.ca.gov | |
Right of Way Phase |
Caltrans | Jackson Ho | (805)276-1114 | jackson.ho@dot.ca.gov | |
Construction Phase |
Caltrans | David Silberberger | (805)549-3798 | david_silberberger@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | David Silberberger | (805)549-3798 | david_silberberger@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $0 | $0 | ||||
CMIA |
$28,325 | $2,500 | $30,825 | ||||
Non-bond Funding | |||||||
State/Federal* |
$44,950 | $-2,500 | $42,450 | ||||
Local** |
$17,875 | $0 | $17,875 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $91,150 | $0 | $91,150 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$4,750 | $0 | $4,750 | $4,749 | |||
Design(PS&E) |
$6,700 | $0 | $6,700 | $7,249 | |||
Right of Way |
$23,000 | $0 | $23,000 | $17,632 | |||
Construction |
$56,700 | $0 | $56,700 | $51,052 | |||
Total* | $91,150 | $0 | $91,150 | $70,232 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
01/01/2006 01/29/2010 |
|
01/01/2006 01/29/2010 |
100 | 01/01/2006 01/29/2010 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/29/2010 04/02/2012 |
|
04/24/2008 04/18/2012 |
100 | 04/24/2008 04/18/2012 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
01/29/2012 04/02/2012 |
|
04/26/2010 07/31/2012 |
100 | 04/26/2010 07/31/2012 |
0 0 |
|
Begin Construction Phase
End Construction Phase |
09/04/2012 03/18/2015 |
|
09/27/2012 04/28/2016 |
100 | 09/27/2012 04/28/2016 |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
03/19/2015 03/19/2016 |
|
04/28/2016 07/09/2019 |
50 | 04/28/2016 10/13/2023 |
0 -52 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 0 | 0 | |||||
Implementation Date | 0 | 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 884 | 662 |
Peak Period Time Savings (minutes) | 6424 | 5479 |
Bond Funding Cost | |
---|---|
Adopted: |
$28,325,000 |
Current Approved: |
$28,325,000 |
Actual Expenditures: |
$22,756,000 |
Status as of December 31, 2023.