San Juan Road Interchange

Description: Near Prunedale, from 0.4 mile south of Dunbarton Road (North) to 1.0 mile north of Cole Road. Convert to freeway and construct new interchange.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Monterey
City Aromas
Zip Code
 
Senate District
15
Assembly District 28
Congressional District 17
 
Caltrans District
05
 
 
County/State Route Monterey 101
Postmile Begin/End 100 101.3
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  884    662  
Peak Period Time Savings (minutes)  6424    5479  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans David Silberberger (805)549-3798   david_silberberger@dot.ca.gov
Design (PS&E) Phase
Caltrans David Silberberger (805)549-3798   david_silberberger@dot.ca.gov
Right of Way Phase
Caltrans Jackson Ho (805)276-1114   jackson.ho@dot.ca.gov
Construction Phase
Caltrans David Silberberger (805)549-3798   david_silberberger@dot.ca.gov
 
Corridor System Management Plan
Caltrans David Silberberger (805)549-3798   david_silberberger@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $0 $0
CMIA
$28,325 $2,500 $30,825
Non-bond Funding
State/Federal*
$44,950 $-2,500 $42,450
Local**
$17,875 $0 $17,875
Non Budgeted ETC
$0 $0 $0
 
Total**** $91,150 $0 $91,150

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$4,750 $0 $4,750 $4,749
Design(PS&E)
$6,700 $0 $6,700 $7,249
Right of Way
$23,000 $0 $23,000 $17,632
Construction
$56,700 $0 $56,700 $51,052
 
Total* $91,150 $0 $91,150 $70,232

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2006 

01/29/2010 
 

 
01/01/2006 

01/29/2010 
100  01/01/2006 

01/29/2010 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/29/2010 

04/02/2012 
 

 
04/24/2008 

04/18/2012 
100  04/24/2008 

04/18/2012 


Begin Right of Way Phase

End Right of Way Phase
01/29/2012 

04/02/2012 
 

 
04/26/2010 

07/31/2012 
100  04/26/2010 

07/31/2012 


Begin Construction Phase

End Construction Phase
09/04/2012 

03/18/2015 
 

 
09/27/2012 

04/28/2016 
100  09/27/2012 

04/28/2016 


Begin Closeout Phase

End Closeout Phase
03/19/2015 

03/19/2016 
 

 
04/28/2016 

07/09/2019 
50  04/28/2016 

10/13/2023 


-52 
Corridor System Management Plan
Adoption Date        
Implementation Date        
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 884 662
Peak Period Time Savings (minutes) 6424 5479

Bond Funding Cost
Adopted:
$28,325,000
Current Approved:
$28,325,000
Actual Expenditures:
$22,756,000

 

Status as of December 31, 2023.